The project is terminated before completion. The project sponsor indicates the reason for the termination is a lack of funds. Which of the following actions should the project manager take next?
A、Request the sponsor find alternative ways of funding the project and suggest certain references, e.g. seeking loans from financial institutions.
B、Request a project manager from another project to initiate steps needed to fund their project.
C、Brainstorm with the project team to find sources of funding for the project.
D、Transfer lessons learned and historical information to the lessons learned knowledge base for used by future projects.